Construction of temporary hardstand for vehicle laydown whilst minimising disruption to existing Nowergup Depot operations.
The project involved placement and compaction of 150mm of road base to achieve 98% MMDD in compliance with the PTA specification. Pennant was also required to direct drainage to existing catchment points nominated by the client.
Pennant successfully completed the project within a two weeks window for timely handover of area to the client for use.